The concrete is here!

Despite the rain that came down over the last few days, the base of the new road is in a very good condition. In fact, it's never been as good.

Last night Mariano came down for a drink and to let us know that they would be starting to lay the concrete today.  But as there were no "pista cortada" notices, could we park our car outside so nobody could get past. Well, no.  Didn't think that was a very good idea at all, so instead we made a sign which we attached to some orange fencing and strung that across the pista so no-one could get through.

First up today was the grader doing a final check, then a lorry delivering sheets of steel mesh, 8 workmen and then  the first concrete mixer.  The workmen are laying the mesh and putting in metal edges for a mold, which will be taken out later.  They have set up a 'hopper' for mixing the cement and  gravel  down in Yator - quicker and needs less mixers.

By 5.30 pm they were about 400m or so from us, obviously working from the top  downhill.   Spoke to the 'jefe' this morning, he reckons about 6 or 7 working days.  Not sure exactly when it'll be driveable - but I'm sure we'll find out when someone comes up and can't get through our road closed sign. 
Delivering the mesh and the first mix load.

We assume that when they finished work tonight, they've left a machine/roller or something across the end of the Yator end to stop traffic.

Tuesday, 30 November 2010

Is it winter already?

After a few days of persistent drizzle and a forecast that includes light snow overnight, I'm beginning to wonder what has happened to Autumn!

We've been hunkered down indoors, tiling kitchen walls,  keeping the wood burners stoked up  and taking the dogs for wet walks.  How far we go depends on how wet it is, steady drizzle I don't mind but when it blows inside your hood and trickles off your raincoat and inside your boots - well, then it's time to come home and dry off.

We'd just finished lunch today, made a cup of tea and I was thinking about another wet walk when the electric went off.  We expect brief power cuts when it's bad, especially when there's snow or high winds around, but at lunch time it wasn't any of those things so we thought it'd be a brief cut-off.  But no, it was much longer.  It went off at 2pm and by 6pm when it was getting gloomy indoors we lit candles in the lounge and found the 'bluey'.  I don't know the proper name for the bluey, John calls it that.  It's a blue portable gas bottle,  its  flame has a glass cover over it,  we inherited it with the house.  I think it's probably something campers might use?  Anyway, it only comes out once in a blue moon and we'd only had it and the candles alight for about half an hour, when the electricity came back on.

We've left everything out though, just in case! 

Saturday, 27 November 2010

Watering Wednesday.

Wednesday and watering day for the new road!

We couldn't hear any noise during the morning on Wednesday and having an hour or so to spare before lunch, thought we'd take the dogs out for a  walk down to Yator.  It's a long walk for them because they run backwards and forwards and go about 3 or 4 times as far as we do.  We dropped in on some friends for a coffee and a chat and left about an hour later to head back up the hill and home for lunch.

As we reached the cemetery, the water bowser lorry was coming down and  spraying as he went.  He turned round and set off back up followed by us - still spraying water and with us trying not to get our feet too wet.  Following behind us was the road grader spreading the gravel more evenly and then behind him came the road roller packing it all down.  The roller spent all afternoon going backwards and forwards, it also has some sort of vibrating mechanism to pack it down more solidly.

We had a chat with the driver of the water bowser,  he said it holds about 10,000 litres of water.  He also said  that when they start laying the concrete, it will take about a week to 10 days and obviously many, many lorry loads!

Monday, 22 November 2010

More machinery.

We were right about the steam roller, except it wasn't a steam one, more than likely a diesel roller!  

First up on Friday was a  tractor pulling a water bowser.  They were used a lot when the road  was built between Yator and Cadiar,  the bowser sprays water onto the surface ready for the roller to pack it down.   The driver adjusted the spray from a fine spray to what seemed to be a drenching.  The road surface looked very soggy but after the roller had been up and down a few times it was solid again.  They repeated this on Saturday morning.

Then this morning the road grader reappeared, stopped at the end of the new road and waited for a while until a truck appeared.  The big Cat has made a large area below Cortijo la Loma, which is about 500 metres away on the way to Yator.  The trucks have enough space there to park, wait and turn around.  But from there to us is uphill and there are  also about 6 curves in the track.  The trucks came from there in reverse to dump their loads of gravel before driving down for a refill.  There were 3 trucks altogether coming and going all day, with the grader levelling out the gravel behind them.  It looks quite a thick layer of gravel that's been laid.

By the end of tomorrow, they should have finished.   And then - well, we'll have to  wait and see what comes next.

Thursday, 18 November 2010

Rain, what rain?

Well, the promised rain - or at least the chance of some drizzle - never happened.  The most we got was a few drips yesterday morning and I think there might have been some late one evening too.  Can't remember  which day it was!  All I know is that we have planted about 500 broad bean seeds this week and then watered them in - they should provide the ground and composts with some really good nourishment in the spring.

Most of the leaves have dropped off the trees and been swept up ready to be layered in the compost and we have dried plants, twigs and such like to go through the chipper and into the compost as well.  The chipper has been very poorly recently, it wouldn't start so there was no point taking it up to the composts ready to work.  J  had to strip the engine down and try everything, clean spark plugs and other things that mean nothing to me.  Eventually it was found to be a problem with the fuel getting to the carburettor.  It all looked a bit complicated and oily and  there was lots of to-ing and fro-ing to the user manual.   The first 18 or so pages were health and safety do's and dont's - all he needed was the 'exploded'  picture of the engine and it's components.   But finally it started with a roar,  lots of dirty exhaust fumes poured out and then it settled down to it's usual chug chug sound.  So tomorrow it's up to the compost terrace with it to get that area shredded and tidied.

The road builders are still out there 'draining' and late this afternoon the grader came up and worked it's way back down.  Maybe this is the last re-grade before the concrete?!   We can see another machine parked just off the road below us, but can't see quite what it is.  I think it's a steam roller....time will tell.

And an added extra:  the sun has just gone down leaving behind some amazing streaks of colour.